Project Code Building
Scope MEP
Work Description

3B+G+14 Commercial Building, on Plot #  373-1323 - Al Barsha 1st, Dubai - UAE

Built Up Area: 11,600 m²



3 Basement Car Parking + Ground Floor Entrance Lobby + 14 Floors Offices. 


Engineering, Procurement, Installation & Commissioning of Complete MEP Works including Central Air Conditioning and Ventilation Systems, Plumbing and Drainage Systems, Fire Fighting System, Electrical  Low Voltage and Low Current Systems


Cooling Load: 2 Air Cooled Water Chillers of 121 TR each

Connected Load: 5 Nos. MV Transformers of 1000 KVA each




Value AED AED 11,471,602.22
Client Mr. Thani Abdullah Mohamed El Shirawi
Main Contractor 
Period Dec-07 to Dec-09